Grid Level 3 (NE3) comprises the high-voltage grid with a typical voltage of 110 kV. It forms the connection between the supraregional extra-high-voltage grid (NE1) and the regional medium-voltage grids (NE5). At this level, electrical energy is distributed to cities, large industrial facilities, and substations, which further transform the electricity.
Function and Importance of Grid Level 3
The NE3 high-voltage grid is used for the large-scale distribution of electricity. It transports electrical energy from the substations at the extra-high-voltage level to the regional distribution grids. In addition, electricity from medium-sized power plants and renewable energy sources such as wind and solar farms is fed into the grid at this level. Large industrial facilities and Deutsche Bahn also draw their electricity directly from the 110-kV grid.
Technical Characteristics
- Voltage level: Typically 110 kV
- Grid structure: Meshed or ring topology to increase supply reliability
- Components: Overhead lines, switchgear, transformers, and substations
Grid Level 3 is crucial for the stability and efficiency of the power supply in regional areas. Its structure enables flexible control of power flows and a reliable supply to connected consumers.
Role of Netzkontor GmbH
Netzkontor GmbH supports grid operators in the planning, expansion, and maintenance of high-voltage grids at Grid Level 3. With our expertise, we help ensure that the energy supply is efficient and future-proof.